Contact: Jennifer Wright

Phone: (915) 790-4340

Date: Jan. 12, 2018


I-10/Americas - Phase IV Project

Thursday, Jan. 18 (complete closure)
8 p.m. to 5 a.m. (overnight)

  • I-10 westbound between Don Haskins and Zaragoza overpass
  • Loop 375 southbound to I-10 west connector
  • Loop 375 northbound to 1-10 west connector
  • Crews will be doing striping.

Joe Battle (Loop 375) Widening Project

Monday, Jan. 15, through Friday, Jan. 19 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • Northbound closure along Loop 375 between Bob Hope overpass to Vista Del Sol overpass
  • Entrance ramp at Pellicano
  • Entrance ramp at Vista Del Sol
  • I-10 westbound to Loop 375 northbound connector
  • I-10 eastbound to Loop 375 northbound connector

Illumination Work

Monday, Jan. 15, through Friday, Jan. 19
9 a.m. to 4 p.m. (as needed until further notice)

  • Purple Heart Highway (Loop 375) northbound and southbound alternating lane closure between Railroad Drive and Montana Avenue (US 62/180)
  • Crews will be installing conduits and illumination assemblies.

Alameda Reconstruction Project

Through Friday, Mar. 30
9 a.m. to 4 p.m. (as needed until further notice)

  • Alameda Avenue (SH 20) alternating lane closures westbound and eastbound will be reduced to one lane between Inglewood Road and Carnes Road.
  • Closures are necessary for placement of new drainage/waterline, concrete paving, sidewalk and illuminations.

Fabens Bridge Project

Through Friday, Feb. 16, 2018
(continuous complete closure)

  • North Loop Road (FM 76) between Hunt Drive and Alameda Avenue (SH 20)
  • Crews will be removing and replacing intersections.

Striping Project

Monday, Jan. 15, through Friday, Jan. 19
8:30 p.m. to 6 a.m. (overnight)

  • Cesar Chavez Highway (Loop 375) eastbound – 2 inner left lane closures between US 54 overpass and Midway Drive
  • Crews will be doing striping.

Mall Braided Ramp Project

Monday, Jan. 15, through Thursday, Jan. 18 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • I-10 westbound between Yarbrough overpass to Airway overpass
  • Yarbrough overpass to Airway overpass - all entrance and exit ramps
  • Crews will be drilling for high mast on right shoulder.

Until further notice

  • Gateway East reduced to one lane between Airway Boulevard and Hawkins Boulevard
  • Gateway West reduced to one lane between Viscount Boulevard and Hawkins Boulevard

Closed until further notice

  • I-10 eastbound Hawkins exit ramp
  • I-10 westbound Hawkins exit ramp

TxDOT Darrington Road

Thursday, Jan. 18, through Friday, Jan. 19 (complete closure)
9 a.m. to 9 a.m. (traffic switch from Phase 1 to Phase 2)

  • Alberton to LTV Road – All southbound traffic will be closed and switched to northbound lanes.
  • Crews will be reconstructing southbound lanes.

Deceleration Lane/Driveway Project (Note: This is not a TxDOT project.)

Expect these closures every Monday through Friday until further notice:
9 a.m. to 4 p.m. (at different times throughout the day)

  • Horizon Boulevard (FM 1281) southbound right lane closure at Darrington Road
  • Zaragoza Road (FM 659) northbound right lane closure between Sun Fire and Charles R. Schulte Drive
  • Gateway East Boulevard right lane closure between Pendale Road and Kessler Drive

Please follow the detour signs in place on all projects. All work is dependent upon weather conditions.

###

The Texas Department of Transportation is responsible for maintaining 80,000 miles of road and for supporting aviation, rail, and public transportation across the state. Through collaboration and leadership, we deliver a safe, reliable, and integrated transportation system that enables the movement of people and goods.  Find out more at TxDOT.gov. "Like" us on Facebook and follow us on Twitter.